May 4, 2021 1:30 PM

Village Road Construction - Moore Avenue

The Village will be continuing/completing their road construction on Moore Ave, Webster Ave, Dryer Ave and the North parking lot (behind East Main businesses) starting May 10th.

Moore Ave and North Parking Lot – Tentative Construction Schedule:
Week of May 10th – Milling and Drainage
Week of May 17th – Drainage
Week of May 24th – Drainage
Week of May 31st / 1st of June – Prep and Pour Curb Moore Ave
Week of June 7th – Topsoil, Seed, Driveways on completed curb side
Week of June 14th – Prep and Pour Curb, other side (impacts the entrance/exit off Moore Ave)
Week of June 21st – Topsoil and Seed, Install Driveways
Week of June 28th – Finish Topsoil and Seed, Driveways and Prep for Blacktop
Week of July 5th – Oil and Stone with Town & Village
Week of July 12th – Pave Binder on Moore Ave
Week of July 19th – Prep for Top of Moore Ave and North Parking Lot
Week of July 26th – Landscape and Clean-up